Crocus Creek Wall Slated To Be Completed By Next Week

By Lawrence Harris on July 22,2008

image

After almost 2-months of construction the Crocus Creek retaining wall and Melson Ridge Road project will be completed next week.
According to Adair County Judge Executive Office Administrator Lisa Lee the Adair County Road Crew took down the concrete forms yesterday and will begin back filling the area between the 310-foot long, 12-foot high wall today or Wednesday.
The wall was built to keep the creek from washing away a large section of Melson Ridge Road that was in jeopardy of collapsing.
The road crew poured the third and final top section of the wall last Friday and will now start the process of filling the entire length behind the wall with dirt, rocks and sand.

 

Photo: Members of the Adair County Road Department guide the concrete while pouring the third and final section of the Crocus Creek wall project last Friday. (Photo by Lawrence Harris)
 